St.Mina Gym Project

St.Mina Gym Project Update

Progress on Oct.01.2018:

* Exterior walls painting started

* Dry wall installation inside the gym completed and mud and tape is going on

* Steel studs framing in mezzanine floor and main floor is completed

* HVAC and Plumbing installation is going on

[

 

 