St.Mina Gym Project

St.Mina Gym Project Update Progress on Oct.01.2018: * Exterior walls painting started * Dry wall installation inside the gym completed and mud and tape is going on * Steel studs framing in mezzanine floor and main floor is completed * HVAC and Plumbing installation is going on [    