St.Mina Gym Project Update

Current Progress:

  • Sept.29.2017: Obtained Development Permit Approved from Rockyview County
  • Sept.22.2017: Received 3 proposals from Contractors ( Clark Builders, NVR & Genesis) for the Construction Management Service for the project
  • Sept.16.2017: ATB submitted the mortgage application for the underwriter approval
  • July.21.2017: Responded to the comments on DB from Rockyview county
  • Jul.12.2017: Received Conditional Approval for the development permit application from Rockyview County
  • May.07.2017: Submitted Development Permit Application
  • March.& April: 2017: Selected the surveying company, selected the Soil testing company, selected the Civil design consultant , selected the parking study consultant & selected the landscaping consultant
  • Feb.08.2017: Signed contract with Transept Architecture Inc. to start the design work for the Gym project
  • Sep.2016-Dec.2016: Assessment of different buildings types (Conventional Building, Sprung Structure & Pre-engineered Buildings). The selected building type is the Pre-engineered Building and selected supplier is Ironwood Building Corp. 

Next Steps:

  • Complete the detailed drawings to apply for the Building Permit by end of Oct.2017
  • Select the CM contractor 
  • Sign the contract with Ironwood to start the steel fabrication